Ministry of Fisheries & Aquatic Resources .
Department of Fisheries & Aquatic Resources
 ACTION PLAN - 2009
Head 290 Programme  01 Project  01
(1) (2) (3) (4) (5) (6) (7) (8)
Prog. Project Activity Milestones 2009 Annual Target Allc.  Financial Target   Responsible for
1st  2nd 3rd 4th  2009 1st  2nd 3rd 4th  implementation
      Quarter  Quarter  Quarter  Quarter    (Rs.Mn) Q Q Q Q (Designation & Tel. No.)
Conservation   x. Repairs of toilet system of Estimated & TEC approved & Repairs  
 
         
 
and        A.D.office & A.D. quarters  Tendre called Tender opperd compleated              
development      of Puttalam.                    
of fishery               0.500     0.250 0.250  
resources   xi. Repairs of toilet system of Estimated & TEC approved & Repairs              
        Kalpitiya F.I. office. Tendre called Tender opperd compleated              
                           
    xii. Provided water & toilet Estimated & TEC approved & Repairs     0.150     0.150    
          facilities for Kapparatota Tendre called Tender opperd compleated      District offices          
          F.I. office.             Maintained                Dy.Director (Admin.)
                  in good                   Tel: 2438010
    xiii. Construction parapat wall Estimated & TEC approved & Repairs Construction       conditioned. 0.700     0.200 0.500  
           & gate & Repairs of Toilet Tendre called Tender opperd compleated compleated            
           & windows of F.I. office in                     
           Payagala.                    
                           
    xiv. Partition of A.D. office & Estimated & TEC approved & Repairs     0.300   0.200 0.100    
           colour wash of Kinniya & Tendre called Tender opperd compleated              
           Muttur F.I. Office.                    
                           
  Acquisition of Construction of  Construction  Construction  Construction  Construction  Jaffna District 5.300 1.500 2.000 1.000 0.800  
  fixed assets and Jaffna District Office continued continued continued Completed office building             
  new construction         Constructed            
  2104 -  5.3 M                      
                           
  Rehabilitation and Rehabilitation of  Rehabilitation  Rehabilitation  Rehabilitation  Rehabilitation  Machinery and 
 
         
  improvement of  machinery and  work attended work attended work attended work completed  equipment                  Director / Finance
  Plant, Machinery  equipment at Head         maintained in                   Tel: 2472185
  and Equipment office and Districts         good condition            
  2002  -  1.2 M                        
                1.200 0.100 0.200 0.500 0.400  
Monitoring Controlling     &             Surveillance   Rehabilitation work of Radio Communication/ Antenna Systems at all (22) MCS centers and repairs of equipments. Rehabilitation work and repairs of equipment attended Rehabilitation work and repairs of equipment attended Rehabilitation work and repairs of equipment attended Rehabilitation work and repairs of equipment completed. MCS centers maintained well        
 
 Director (MCS)                                     Tel.011-2472529
                        Total 12.300 2.050 3.800 3.500 2.950  
2
4.150 0.450 1.400 1.300 1.000 4.15
8.150 1.600 2.400 2.200 1.950 8.15
12.3